LaPorte Ground Site Timeline
Last updated 21 July 2000
- Fencing work completed by 28 July 2000
- Power installation finished and power available by 28 July 2000
- Scaffold platforms installed and available by 1 August 2000
- Lighting and flag markers are required by the FAA.
- Portable toilets delivered before 4 August 2000
- Telephone and Internet service available (Site B only!) by 4 August 2000
- Rented trailers delivered, setup, and powered by 5 August 2000
- Site A: 7 trailers needed, Model 825 (which are 8' x 20') set-up according to the site layout. The trailer numbers are: 2, 5, 6, 7, 9, 10, and 11. The trailers should be tied down and have steps installed.
- Site B: 7 trailers needed, Model 825 (8' x 20' ) set-up according to the site layout. The trailer numbers are: 15, 16, 17, 18, 19, 20, and 21. The trailers should be tied down and steps installed.
- On-site storage containers delivered by 5 August 2000
- 8' x 8' x 20' metal sea-containers used for dead-storage on site (and for Paul Tanaka's smog chambers) should be placed, on the ground, according to the Site A and B layouts.
- Tables and chairs delivered on 7 August 2000
- 32 tables (30" x 60") and 36 folding chairs (padded) needed. There will be an allowance with this vendor to add or substract tables and chairs as needed.
- Instrumentation installations may begin no earlier than 6 August 2000. Refer to Shipping/Storage.